Project Schedule
The project is currently in the enclosures and interior work phase. A construction site perimeter fence is installed to provide appropriate protections during the construction period.
Work is expected as follows:
- Spring–Summer 2020: Mass excavation
- Fall–Winter 2020: Foundation and concrete work
- Spring 2021: Steel work
- 2021–2022: Enclosures and interior work
- First half of 2023: Project completion
For questions and comments, please share your thoughts using our online form.
-
About the Project
In June 2018 the museum announced its plan to create a new work of signature architecture on the north end of the its historic campus.
Learn More -
Project Partners
Learn more about our architectural partner, OMA, and the project's construction manager, Gilbane.
Learn More -
Project History
Trace the evolution of the museum's campus development project from 2012 to the present.