Project Schedule

The project is currently in the enclosures and interior work phase. A construction site perimeter fence is installed to provide appropriate protections during the construction period.

Work is expected as follows:

  • Spring–Summer 2020: Mass excavation 
  • Fall–Winter 2020: Foundation and concrete work
  • Spring 2021: Steel work
  • 2021–2022: Enclosures and interior work
  • First half of 2023: Project completion

For questions and comments, please share your thoughts using our online form.

  • About the Project

    In June 2018 the museum announced its plan to create a new work of signature architecture on the north end of the its historic campus.

  • Project Partners

    Learn more about our architectural partner, OMA, and the project's construction manager, Gilbane.

  • Project History

    Trace the evolution of the museum's campus development project from 2012 to the present.

  • Make a Gift

    Your donation in any amount to our Capital Campaign makes a difference.